Steps to Build a Warehouse in Indonesia



Steps to Build a Warehouse in Indonesia requires 14 procedures, approximately takes 160 days, and costs 173.27 % GNI per capita to build a warehouse in Indonesia.

Bellow Step to Complete Build a warehouse in Indonesia :


1. Request Pre-approval letter from Zoning Department
Time : 1 day
Cost : IDR 1,482,000

2. Receive inspection from Zoning Department
Time : 1 day
Cost : no charge

3. Obtain Pre-approval letter from Zoning Department
Time : 20 days
Cost : no charge

4. Request and obtain notarized copy of Land Ownership certificate *
Time : 1 day
Cost : IDR 25,000

5. Request and obtain the preparation of the Environmental Management Plan (UKL) and Environmental Monitoring Plan (UPL)
Time : 8 days
Cost : IDR 15,000,000

6. Request and obtain the approval for the Environmental Management Plan (UKL) and Environmental Monitoring Plan (UPL)
Time : 10 days
Cost : no charge

7. Request and obtain building construction permit (IMB)
Time : 21 days
Cost : IDR 9,104,200

8. Request and obtain the building completion and compliance minutes
Time : 28 days
Cost : IDR 62,500

9. Obtain building usage permit (IPB)
Time : 49 days
Cost : no charge

10. Register with land and building tax office
Time : 11 days
Cost : no charge

11. Register the warehouse with the regional office of the ministry of industry and trade
Time : 9 days
Cost : IDR 100,000

12. Obtain electricity connection *
Time : 8 days
Cost : IDR 12,500,000

13. Obtain water and sewerage connection *
Time : 8 days
Cost : IDR 2,000,000

14. Obtain phone connection *
Time : 4 days
Cost : IDR 500,000

*It takes place simultaneously with another procedure.